Know the requirement.
Review the approved detail and submittal with the trade leads. Agree on one installation method and identify which checks need to happen before the work is concealed.
Readiness & QA/QCQuality and issue closure guide
SLA360 / PRACTICAL PROJECT DELIVERY
Before you bring the owner and trades together for a witnessed test, you need to know what is installed, what has been checked and who owns the remaining work. We help your superintendent and quality lead get those answers.
QUALITY / ASSURANCE & CONTROL
In quality assurance, we agree with your team on the detail, acceptance criterion, timing and person responsible. In quality control, we check the installation against those decisions. A check before a ceiling closes gives the trades time to correct a misplaced sensor while they still have access.
Review the approved detail and submittal with the trade leads. Agree on one installation method and identify which checks need to happen before the work is concealed.
Identify the installed equipment by tag and location. Record the field reading or observation, what differs from the requirement and who will follow up.
Walk the correction with the responsible trade. Attach the new reading, photograph or retest record and flag anything that will affect the witness date.
A damper can show “open” while its blades stay shut. The installer checks the linkage. The controls technician identifies whether the graphic shows a command or actual position. During witnessed commissioning, the team runs the approved sequence and records the observed blade travel and required airflow response. At turnover, the operator can see what was tested, what passed and what still needs attention.
Our scope names who performs each check and who witnesses the result. The contractor manages construction quality, the designer resolves design questions and the owner retains acceptance authority.