TOTAL BUILDING
COMMISSIONING.

Commissioning for new buildings, existing facilities and continued operation.

Which system are you being asked to accept? We help your team agree on what to test and who needs to see it. Your operators can then trace the recommendation to a field result and see what still needs attention.

NEW & EXISTING BUILDINGSWHOLE-BUILDING SYSTEMSPERFORMANCE IN OPERATION

THE PURPOSE OF Cx

The real measure:
did we reduce risk?

A completed checklist matters when it helps the team make a better decision. Will the facility be ready? Will the systems work together? Will the operators understand what they are taking over?

We bring your operators into planning alongside designers, contractors and vendors. Together we agree what the facility must do, follow the tests and record who owns each correction or deferred check. Your team can see what is ready to accept.

Mechanical. Electrical. Plumbing. Controls. Enclosure. The interfaces between them are part of the work.

Total building Cx coordinates the selected systems and their interfaces. New-construction, existing-building and ongoing Cx describe when and how that process is applied. Monitoring supports investigation and follow-through. Enclosure, electrical and data verification add discipline-specific scope to the project’s Cx plan.

PRACTICE. STANDARDS. EDUCATION.

Experience that informs the work.

Marcus Myers, SLA Partner & CTO, brings Cx delivery, commissioning education and active standards leadership across healthcare, laboratories, campuses, commercial and residential buildings, aviation, central plants and industrial facilities. That experience connects the project requirements with field verification and the people who will operate the facility.

Explore the project experience →
Chair
ASHRAE Guideline 0.3P
Ongoing Commissioning
Chair
ASHRAE Guideline 1.7P
Semiconductor Facilities Cx
Voting participation
ASHRAE SSPC 300
Guidelines 0, 0.2 & 1.6P
Commissioning standards, the Cx process, existing buildings & data centers

SSPC 300 is ASHRAE’s Standing Standards Project Committee for commissioning. It coordinates the development and maintenance of Cx standards and guidelines. Guidelines 0.3P, 1.6P and 1.7P are in development. Meet the people behind SLA →

01

NEW CONSTRUCTION Cx

From requirements to a working facility

Build performance
into the project.

The time to define success is before the equipment arrives and the testing schedule gets tight.

We help the owner establish the Owner’s Project Requirements, review how the design team’s Basis of Design addresses them, and develop a Cx plan that connects the systems, responsibilities and acceptance criteria. That gives design reviews, submittals, field observations and testing a common purpose.

As construction progresses, we work with the team on installation quality, startup, controls and testing readiness. Functional and integrated testing then demonstrate the required response, including the operating modes and interfaces that matter to the facility. We track findings through the responsible team’s response, correction and verification.

Explore new-construction Cx experience

Two professionals reviewing drawings at a construction site
PLAN

Make the requirements usable.

Define system boundaries, sequences, test conditions, responsibilities and the evidence needed at each milestone.

DEMONSTRATE

Follow the actual response.

A pump command, a running indication and demonstrated flow are different observations. The test needs to connect them.

HAND OVER

Prepare the receiving team.

Plan operator training early, verify its delivery, and assemble a usable Systems Manual with verified results, operating information and assigned open or seasonal work.

The result is a clear record of what was demonstrated, what was corrected and what still requires attention. The owner can make acceptance decisions with the evidence in view.

02

EXISTING BUILDING Cx · EBCx

Understand the building you have
Air-handler coil piping with multiple offsets, exposed fittings and gaps in insulation at bends and connections
A FIELD QUESTIONWhat is the building telling us?

A trend may point to a problem. Looking at the installation helps the team understand why it is happening.

Find the cause.
Improve the response.

Buildings change. Occupancy, equipment, schedules and expectations do too.

EBCx starts with the owner’s Current Facility Requirements and the people who operate the building. We review records, inspect systems, examine sequences and trends, and investigate the conditions behind comfort complaints, inefficient operation or unreliable performance.

Renovations and equipment replacements can require both existing-system investigation and Cx of new work. We define those boundaries and the applicable owner requirements in the project plan.

The investigation becomes a prioritized improvement plan, distinguishing operating adjustments, maintenance and repair needs, and potential capital work. With the owner and responsible teams, we coordinate the work around occupancy, access and operating needs, then verify the approved corrections.

Updated sequences, operator information and deferred or seasonal checks help the facility keep the benefit after the investigation ends.

Explore existing-building Cx experience

RETROCOMMISSIONING · RCx

When the systems were not previously commissioned.

Establish the current requirements and apply the Cx process to the existing installation and its actual operation.

RECOMMISSIONING · ReCx

When commissioned systems need another look.

Use previous Cx records alongside today’s requirements to evaluate changes, recurring issues and performance that has drifted.

Current SLA experience: ASU Mercado Buildings B and C

Marcus led SLA’s existing-building Cx and closeout work for rooftop HVAC equipment, connecting checkout, testing and balancing records, controls verification and corrective-action records in the final Cx report and turnover package.

See the Mercado rooftop-unit field check
03

ONGOING Cx · OCx

A continuing commitment to performance

Performance changes.
Stay with it.

The building keeps operating after the project team leaves. Its performance needs an owner, a plan and follow-through.

OCx carries new-building or existing-building Cx into continued operation, keeping systems aligned with current facility requirements. We use the commissioning records to establish review responsibilities, performance criteria and a testing strategy, then revisit them as the building changes.

That work can combine operator feedback, site visits, functional checks, seasonal reviews and monitored data. Findings lead to investigation, assigned action and verification. Changes in occupancy, equipment, sequences or operating priorities feed back into the plan.

Illustration of two professionals comparing building automation trends across several days against an operating schedule.

Keep the requirements current. Agree what good performance means as the facility’s use and conditions change.

Keep responsibility visible. Give each finding an action owner, a response path and a verification record.

Keep the result in view. Update the operating information and review whether the improvement holds.

ONGOING Cx IN PRACTICE

From a finding to a verified result.

Follow the review through field investigation, agreed action and verification. Hover or focus to pause; select a step to keep it in view.

OCx
Review. Act. Verify.

01 / Review

Review trends and operator feedback.

Look for changes in schedules, load, comfort and system response. Record the indication and the conditions around it.

Evidence carried forward

A dated review with the equipment, operating mode and supporting observations.

MBCx can support this continuing process with monitored evidence. The review cadence, field work and response responsibilities are set for the program. Any savings claim also needs an appropriate baseline and a record of relevant operating changes.

04

MONITORING-BASED Cx · MBCx

Operating data with a purpose

Turn operating data
into verified action.

Tested at turnover and operating correctly under real load are two different questions.

Our MBCx plans connect the owner’s operating goals and approved sequences to BAS trends, meter data and meaningful key performance indicators (KPIs). We check the data, compare performance under relevant operating conditions, and turn findings into assigned actions. Each correction needs verification, with continued review to see whether the improvement holds.

See SLA’s monitoring and integration work

LEED and owner programs. MBCx can support the LEED Enhanced Commissioning monitoring pathway or a defined operational assignment. The applicable rating-system version, documentation, reporting cadence and responsibilities are established for each project.

Academic-building exterior reference from SLA’s MBCx planning material
FROM SLA’S PROJECT PLANSUse the right data.

Start with the reliable points needed to answer the operating question. Trending every available point is not the objective.

  1. 01

    Goals & reliable data

    Agree the operating question and required points. Check identity, units, timestamps, intervals, retention, completeness and sensor or meter evidence.

  2. 02

    KPIs & comparison

    Define each KPI’s equipment or meter boundary, calculation, units and review period. Agree a baseline and investigation trigger that reflect relevant weather, occupancy, load and operating mode.

  3. 03

    Assigned action

    Investigate the finding with operating and field evidence. Record its impact, responsible party, next step and agreed verification criteria.

  4. 04

    Verified correction

    Review new data or targeted tests after correction. Record what was demonstrated and continue reviewing for recurrence.

ILLUSTRATIVE OPERATING EXAMPLE

Why is the air handler running overnight?

A useful KPI is fan-running hours outside approved operating and support schedules during the review period. Use reliable status data, expose missing intervals and confirm exceptions with the facilities team. A legitimate overnight need, a hidden override and stale data require different responses.

THE ISSUE RECORD
  1. Open
  2. In progress
  3. Resolved, awaiting verification
  4. Closed, verified

Your team receives KPI definitions, data-readiness and baseline records, an active issues log, performance summaries and verification records. Fault detection and diagnostics (FDD) software can help prioritize review within the MBCx process. An alert starts an investigation; it does not establish the cause or authorize a controls change. Software, analyst coverage, review cadence and response commitments follow the agreed scope.

05

BUILDING ENCLOSURE Cx · BECx

The building’s first line of performance

Performance starts
at the enclosure.

Roofs, walls, windows and foundations have to work together to manage air, water, vapor and heat.

BECx connects the owner’s enclosure requirements with design details, material selections, installation and performance verification. The transitions deserve particular attention: roof to wall, window to opening, penetrations, material changes and below-grade connections.

We bring the team back to the practical questions: where do the layers connect, who is responsible for each interface, and what evidence will demonstrate performance?

ENCLOSURE EXPERTISE Marcus Myers BECxP · CTO & Partner

Marcus brings building enclosure expertise together with Cx, construction and building systems experience, connecting the detail in the drawing with the conditions in the field.

Explore enclosure Cx and assessment experience Explore Marcus’s background
Handheld infrared camera displaying temperature patterns during a thermal survey
READ THE ASSEMBLY. CHECK THE CONDITIONS. A thermal pattern is a clue.

Temperature differences need context. Follow the indication with the appropriate inspection or testing before concluding that moisture or air leakage is present.

BEFORE CONSTRUCTIONCan the details be built and verified?

BEFORE CONCEALMENTHave we checked the connections?

BEFORE ACCEPTANCEWhat does the evidence demonstrate?

FOLLOW THE CONTROL LAYERS

One assembly meets another.
That connection matters.

The enclosure review follows the control layers through details, joints and changes in material. A good product still needs the right connection to the next assembly.

Air
Trace the air-control path through walls, roofs, openings and penetrations. Connect that review to the building’s pressure requirements.
Water
Review drainage, flashing, laps, joints and terminations so the water-control strategy continues across adjoining assemblies.
Heat
Follow insulation continuity and thermal bridges at edges, anchors, openings and changes in assembly.
Vapor
Review vapor control and drying potential against climate and indoor conditions. Air leakage and vapor diffusion are different mechanisms.
Roof membrane being installed at an accessible construction stage

Roofs & transitions

Review membrane seams, terminations and changes in material before the next layer conceals them.

Worker applying material at a glazing joint

Glazing & openings

Connect flashing, seals and adjacent control layers. Coordinate the mockup and test conditions.

Below-grade foundation waterproofing before backfill

Below-grade assemblies

Check continuity, protection and transitions while the waterproofing can still be observed.

DESIGN THROUGH HANDOFF

Review the details.
Stay with the work.

Bring BECx into the project while requirements, details and responsibilities can still be coordinated. Tie observations and testing to the construction sequence.

  1. Define the performance

    Establish the Owner’s Project Requirements, enclosure scope, acceptance criteria and responsibilities in the BECx plan.

  2. Review design & submittals

    Follow the control layers, interfaces, material compatibility and installation sequence. Track review comments with the design and construction teams.

  3. Plan mockups & tests

    Agree representative assemblies, test methods, conditions and specialist assignments before installation proceeds.

  4. Observe before concealment

    Schedule field observations while critical connections remain accessible. Record the location, condition and next action.

  5. Test, correct & verify

    Review specified air, water and other performance tests against project criteria. Follow findings through correction and the appropriate retest.

  6. Carry the record into operation

    Bring together results, unresolved items, maintenance information and agreed warranty-phase follow-up for the owner’s team.

New buildings & major renovations

Start with the intended enclosure performance. Coordinate reviews, mockups, field observations and testing with the work, including connections between new and existing assemblies.

Existing buildings & targeted investigations

Start with the reported condition, available records and operating history. Define an investigation around leaks, condensation, comfort or enclosure performance, then verify the agreed corrective work.

THE ENCLOSURE SERVES THE FACILITY

Campus buildings, laboratories, healthcare, data centers, industrial facilities, civic buildings and the places people live and work bring different operating conditions. We shape the enclosure scope around the facility’s use, exposure, indoor conditions and maintenance needs.

A RECORD THE OWNER CAN USE

What was reviewed.
What was tested.
What still needs action.

The agreed BECx scope brings the plan, review comments, location-based field observations, photographs, test reports and issue record into a traceable handoff. Findings stay connected to their responsible party, correction and verification.

Open items, deferred testing and maintenance responsibilities stay visible so the operating team knows what comes next.

Observation, infrared investigation and air or water testing answer different questions. The Cx plan identifies the applicable criteria, specialist testing assignments, design responsibilities and owner acceptance process. BECx supports the project’s design and construction responsibilities; it does not replace them.

Discuss your enclosure scope

Process references: ASTM E2813, ASTM E2947 and BCxA BECx Best Practices. Building science: ASHRAE Building Envelopes. Applicable editions, test methods and acceptance criteria follow the project requirements.

06

ELECTRICAL Cx

Power, protection and connected systems

Verify the power system.
Demonstrate its response.

A powered facility still needs evidence that its electrical systems will support the required operating conditions.

SLA coordinates electrical Cx from the defined power paths and operating requirements through installation readiness, specialist test records, startup, functional testing and integrated systems testing. The Cx plan identifies the equipment, interfaces, expected response and parties responsible for each activity.

The agreed scope may include switchgear and switchboards, transformers, protective devices, ATS/STS, generators and paralleling, UPS and batteries, PDUs/RPPs, busway and rack distribution, grounding/bonding, control power, meters and EPMS. Required specialist tests remain assigned to the qualified providers performing them.

For a data center, power, cooling and controls must be assessed together. A successful transfer alone does not demonstrate cooling recovery, available control power or accurate operator information. We help plan the shared scenario and follow the evidence through the connected systems.

See SLA’s Central Plant electrical Cx work

Explore electrical Cx experience

Explore electrical Cx scope
Illustration of a team reviewing drawings and a display beside closed electrical switchgear
THE INTEGRATED QUESTIONPower returns. Are the cooling and controls ready?

Define the required recovery and the evidence needed across all participating systems before the test.

READINESS

Connect prerequisites.

Review approved drawings, settings, installation checks, specialist reports and startup records against the next planned activity.

VERIFICATION

Compare expected and actual response.

Coordinate functional and integrated tests, record observations and keep findings connected to correction and retest.

OWNER RECORDS

Make the operating limits clear.

Provide readiness status, witnessed results, interface findings and turnover records, including unresolved restrictions and assigned follow-up.

Cx coordination, witnessing and verification do not replace installation, specialist acceptance testing or equipment operation. Qualified, authorized parties perform switching and testing under approved procedures, risk assessment and site safety controls. The owner’s designated authority makes acceptance decisions.

LIGHTING & LIGHTING CONTROLS

The room is empty. Why are the lights still on?

We ask about lighting controls when we define every building commissioning scope. Where lighting is included, we test the agreed sequence in the rooms it serves.

New construction
We walk the zones with your team and check the response against the approved sequence. Do the right fixtures respond when someone enters or leaves? Where daylight control is specified, does the perimeter dim as daylight increases?
Existing buildings
We compare installed wattage and programmed schedules with actual operating hours. If a zone draws 1 kW for three extra hours, it uses 3 kWh. If the lights stay on, we check the zone assignment, sensor response and local overrides. After an agreed correction, we retest the affected zone.

What your operators receive. For the zones in scope, we record the expected and observed response, applicable settings, override behavior and any open retests.

Talk with Mike or Marcus about lighting controls

Lighting project experience and energy data

Before joining SLA, Marcus’s work included fifth-floor lighting controls at the Inter-American Development Bank headquarters in Washington, D.C., and lighting functional-test documentation at Ko‘ula in Honolulu.

The U.S. Energy Information Administration estimated that lighting accounted for about 17% of electricity used in U.S. commercial buildings in 2018. Actual use depends on the building. Read the EIA estimate.

07

DATA ASSURANCE Cx · DACx

Developed by Marcus Myers

From installation
to integration.

Is your data correct? Would you know if it wasn’t?

SLA installs controls, integrates building systems and verifies the data your operators use. With Data Assurance Cx, we follow a measurement from the field device to the screen where your team makes a decision.

Take a power meter. The dashboard can show a believable load even when the current transformer ratio is wrong. We check the meter setup, compare the reading against a field reference and trace it into your energy information system. If the values disagree, we pinpoint where they diverge and retest after correction.

At turnover, you can see who installed the equipment, who tested and witnessed it, which readings you can rely on, and what still needs attention. Your team has the evidence to make the acceptance decision.

Talk with SLA about verifying your system
Marcus Myers’s Data Assurance Commissioning artwork: a wave of untrusted data approaching a person beneath a Cx umbrella
THE SOURCE

Which instrument?
Which asset?

Verify the installed measurement location, sensor suitability and range. Review calibration or verification evidence, and compare with appropriate reference measurements where the plan requires them. Confirm the asset, units and condition represented.

THE PATH

Does the meaning
survive the connection?

Trace the tested source through point naming, units, scaling and mapping. Check timestamps and quality flags, then compare the value at the operating screen and the related control response.

THE DECISION

Can the receiving
team defend the value?

Provide a point crosswalk, validation records and assigned exceptions. Distinguish verified measurements from unverified, stale, missing or unreliable values before they support operating or investment decisions.

DACx is SLA’s named verification approach developed by Marcus Myers. It is not presented as a published ASHRAE standard or an independent certification.

Current SLA experience: ASU MRI Building

The targeted EIS and metering Cx assignment connects installation readiness, point-to-point checks, meter identity and functional-verification planning to the owner’s operating-data handoff.

Explore the MRI metering assignment
Mechanical utility corridor with overhead piping, valves and supporting infrastructure

COMPLEX FACILITIES. CONNECTED SYSTEMS.

The interfaces
deserve attention.

A component can pass its individual check while an important system interaction remains unproven. Critical facilities make those connections especially consequential.

Data centers

Connect power, cooling, controls, monitoring and the agreed operating scenarios. Define the acceptance stages and prerequisites, then carry the evidence into integrated systems testing and operational handoff.

Semiconductor facilities

Follow utilities, automation and support systems to their points of connection. Align facility readiness with supplier requirements, process interfaces and the owner’s acceptance criteria. Facility Cx and process qualification have distinct responsibilities.

Marcus chairs ASHRAE Guideline 1.7P for semiconductor facilities and participates in Guideline 1.6P for data centers. That standards work complements the field and project experience behind SLA’s approach.

DATA-CENTER Cx LEVELS & READINESS

What does each level
actually demonstrate?

Use the stage to connect the equipment, the responsible teams and the evidence for the next activity. Planning and design establish the basis for the acceptance-testing stages. Together, they connect owner requirements to documented system response within the wider Cx process.

Illustrative project legend: L1 red · L2 yellow · L3 green · L4 blue · L5 white. The owner and project team define the levels, colors, evidence and release authority in the Cx plan. This is not a universal ASHRAE color requirement. A Cx status tag does not authorize energization.

FROM DESIGN INTENT TO INTEGRATED RESPONSE

The evidence starts at L0.

Planning makes later testing meaningful. Define the required response, the interfaces and the evidence early, while the team can still resolve gaps before procurement and installation.

Illustrative project sequence. Follow the signal or select a level to hold its explanation. This shows how evidence carries forward, not live project status.

L0

Agree what success means before equipment is purchased.

WHAT CARRIES FORWARD

Owner requirements, design decisions, review comments and the Cx plan become the basis for later checks.

BEFORE THE NEXT ACTIVITY

Are requirements measurable, responsibilities assigned and unresolved design issues tracked?

Read L0 responsibilities and evidence ↓
  1. L0Planning

    Planning & design

    L0 / PLANNING & DESIGN

    Define what must work, how it will be verified and who is responsible.

    An integrated test is only useful when the team knows the required operating response. Early Cx review helps identify conflicting requirements, missing interfaces and testing constraints before they become field problems. The design team remains responsible for the design; Cx reviews and verifies the agreed requirements and process.

    Owner needs → OPR

    Document operating needs, performance targets, loads, modes, maintainability and the conditions the facility must support in the Owner’s Project Requirements.

    Design response → BOD

    The design team explains how its proposed systems and sequences address those needs in the Basis of Design. Track changes against the OPR.

    Cx design review

    Review the OPR/BOD relationship, system interfaces, access for maintenance and testability. Record comments, responsible parties and their resolution.

    Scope & responsibilities

    Define equipment, systems, boundaries and exclusions. Assign who prepares, performs, witnesses, reviews and accepts each required activity.

    Acceptance & test planning

    Set measurable acceptance criteria, required operating conditions, prerequisites and the approach to factory, functional and integrated tests. Develop and refine procedures as the design progresses.

    Tags, evidence & issues

    Agree the level definitions and color legend, asset identification, required records and release authority. Assign issues, track resolution and record any accepted restrictions.

    Prerequisites
    Owner participation, available project requirements, design information and an agreed Cx scope.
    Evidence
    OPR, design-team BOD, Cx plan, design-review comments and responses, responsibility matrix, test strategy and issue register.
    Coordination
    The owner establishes requirements and acceptance authority; designers retain design responsibility; Cx coordinates the agreed verification activities with the project team.

    Handoff check: Carry agreed requirements, measurable criteria, assigned responsibilities and tracked design issues into procurement and subsequent verification.

    L0 is a planning/design label used in some data-center programs. The project’s contract and Cx plan establish its meaning and required records; it is not a universal ASHRAE level designation.

  2. L1Red

    Factory / FAT

    Review the specified equipment performance and configuration before shipment.

    Prerequisites
    An agreed factory procedure, acceptance criteria and identified equipment configuration.
    Evidence
    Factory results, witnessed observations where scoped, deviations and their disposition.
    Coordination
    The manufacturer performs testing; assigned witnesses and reviewers assess the evidence.

    Handoff check: Review the required factory evidence and exceptions before the planned shipment or next activity.

  3. L2Yellow

    Installation verification

    Check that the delivered and installed equipment matches the approved requirements.

    Prerequisites
    Equipment identification, receiving condition and applicable installation requirements.
    Evidence
    Receiving and installation checks, inspection or specialist records, and open items.
    Coordination
    Installing and QC teams provide records; designated reviewers assess readiness.

    Handoff check: Identify remaining installation restrictions and prerequisites for authorized startup.

  4. L3Green

    Startup

    Establish component and subsystem operation before broader functional testing.

    Prerequisites
    Accepted installation prerequisites and authorization under the site’s operating procedures.
    Evidence
    OEM startup reports, applicable settings, prerequisite checks and unresolved issues.
    Coordination
    Qualified OEM and contractor teams perform startup; Cx coordinates evidence review.

    Handoff check: Confirm the defined system is stable and ready for the approved functional tests.

  5. L4Blue

    Functional performance testing

    Demonstrate each system’s required sequence under the agreed operating conditions.

    Prerequisites
    Startup evidence, an approved test procedure and the required system interfaces.
    Evidence
    Expected and actual response, trends, observations, findings and retest status.
    Coordination
    Assigned test teams operate equipment; Cx coordinates and witnesses the agreed scope.

    Handoff check: Review the participating systems and remaining dependencies before the selected IST scenario.

  6. L5White

    Integrated systems testing

    Demonstrate the combined response of power, cooling, controls and monitoring.

    Prerequisites
    Reviewed functional records, defined system/load boundaries and an authorized scenario.
    Evidence
    Coordinated observations, results, exceptions and confirmed restoration status.
    Coordination
    Authorized operating and specialist teams participate; the owner’s designated authority reviews acceptance.

    Handoff check: Carry the demonstrated response, remaining restrictions and next actions into the defined handover.

L6 / TURNOVER & FOLLOW-UP

L6 is a supporting lifecycle label used in some project programs. Organize accepted records, training, operating information, open restrictions and deferred or seasonal verification. The owner’s agreed turnover process governs acceptance and continuing responsibilities.

ASSET IDENTIFICATION & READINESS TAGGING

The color needs a record behind it.

Define the tagging system during L0. Agree what each status means, which records support it and who can authorize a change before tags are used in the field.

A permanent asset ID identifies the equipment. A Cx status tag communicates a defined stage supported by records. Use words as well as color, and distinguish completed testing from readiness for the next activity.

Link the physical label, drawings, controls name, report revision, reviewer, review date and restrictions. Assign who records, reviews and approves each change. After equipment, wiring, settings or software changes, reassess the affected evidence and retest needs.

ILLUSTRATIVE STATUS RECORD

Asset
UPS-01
Current record
L4 results reviewed for the tested modes
Next stage
L5 readiness pending
Open dependency
Cooling-control interface verification
Next action
Resolve the interface item, review its evidence and update the readiness register.

Project records also identify the responsible parties, report revision, review date and acceptance authority.

Keep the authorities separate. Cx status tags are not lockout/tagout devices or operating permits. They do not authorize energization, switching, access or removal of hazardous-energy controls. Applicable safety procedures and qualified, authorized personnel govern those activities. Level completion does not establish Tier or LEED certification.

Technical references

These explain the wider Cx process and project variation. Your contract and Cx plan establish the applicable requirements.

BCxA: acceptance-testing levels and the wider Cx process ↗Uptime Institute: mission-critical Cx and integrated testing ↗

PROJECT-SPECIFIC DETAIL

Technical reference, when you need it.

Facility conditions, system responsibilities and project requirements shape the final assignment. These guides add detail to the services above.

Facility conditionsExamples across nine facility types.

Data centers

Power, cooling and controls must support one operating response.

Readiness depends on the load, operating modes, transitions and recovery conditions the owner needs to demonstrate. An equipment test alone may not show how the connected facility responds.

POWER / LOAD / COOLING / SELECT A CONNECTION

010203

Follow the electrical dependencies.

Review the planned supply paths, controls power and required transitions with the responsible electrical team. Equipment readiness and integrated response need connected evidence.

Illustrative relationships. Scope and acceptance evidence are agreed for each project. No connection to live equipment.

Where SLA’s Cx work connects

  • Electrical and mechanical Cx coordination
  • Cooling sequences, permissives and recovery
  • Controls power, monitoring and operator information
  • Functional and integrated-system test planning

What your team receives

A coordinated readiness and test plan, interface responsibilities, observed results and findings that show what remains unresolved.

Power returns. What happens next?

The planned verification should account for cooling availability, controls power, permissives, communications and alarms, along with the authorized recovery criteria. Switching and specialist testing stay with qualified, authorized parties.

Systems and responsibilitiesElectrical, mechanical, process utilities and QA/QC.

Electrical Cx

Electrical readiness, power-system verification and connected response are explained in the visible scope above.

Read electrical Cx scope →

Mechanical, utilities & integrated systems

Cooling, heating, ventilation, process utilities and controls. Follow the dependencies between equipment, sequences and delivered operating conditions.

What does connected verification involve?

Review the required conditions and interfaces across heating, cooling, ventilation, process utilities and controls. Confirm prerequisites, sequence expectations and vendor responsibilities. Coordinate approved tests around the delivered system response, then document findings, corrections and retests. Contractor startup, TAB and manufacturer activities keep their defined responsibilities.

QA/QC & readiness

Inspection plans, observations, issue ownership, prerequisites, corrections and verified closure. Cx coordinates with contractor QC and specialist testing while preserving their defined responsibilities.

How do findings reach verified closure?

Define observations and readiness checks, record the requirement and affected location, and assign the response. Track correction separately from verification. Document retest evidence, open restrictions and deferred work before the next milestone. Cx quality assurance supports the project while contractor quality control and design responsibility remain explicitly assigned.

Codes, certification and owner requirementsLEED, adopted codes, ASHRAE, owner criteria and specialist guidance.
Open the guide relevant to your project. Official references are included.
01LEED certificationConnect the selected certification path to the actual Cx scope.

What it means

LEED is a building certification program. The Cx work must follow the rating system, version and credits registered for your project. A general request for “LEED commissioning” is not enough to define the assignment.

When it matters

For an owner pursuing LEED on a new building, major renovation or other eligible project, begin with the project scorecard and registration information. Confirm the applicable prerequisites and any enhanced Cx, enclosure or monitoring-related options before pricing or scheduling the work.

How SLA helps connect the work

  1. Define the path

    Review the registered version, selected credits, systems included, Cx provider qualifications and reporting relationships. Distinguish the required baseline from additional credit work.

  2. Carry requirements into delivery

    Review the owner’s project requirements (OPR) and basis of design (BOD). Coordinate the Cx plan, design and submittal reviews, readiness, functional verification and issue resolution within the selected scope.

  3. Prepare the evidence

    Organize the required records and Cx submissions with the certification team. Identify any training, systems-manual, post-occupancy or monitoring obligations that belong to the chosen path.

What your project receives

  • A Cx scope aligned with the selected rating requirements and responsibilities.
  • Review comments, verification records and an issues log showing closure or outstanding actions.
  • Cx documentation and follow-up obligations for the certification and operating teams.

Bring to the first conversation

  • LEED rating system, version and scorecard
  • Design stage, drawings and OPR/BOD if available
  • Certification-team contacts and target milestones

SLA supports the Cx portion of the certification effort. LEED certification is determined through the certification review process; it is not issued by SLA. Options and requirements differ by rating system and version.

Official references, if you want to go deeperUSGBC: rating-system selection ↗
02California Title 24 & CALGreenCoordinate the applicable code work, testing and required records.

What it means

Title 24 contains multiple parts of California’s building regulations. The Energy Code is Part 6; CALGreen is Part 11. A project can have requirements under both. Cx, acceptance testing, design review and closeout documentation must be assigned to the correct parties.

When it matters

For a California project, establish the applicable edition, permit timing, building type and scope before deciding what is required. The 2025 Energy Code includes nonresidential Cx provisions in Section 120.8; applicability and exceptions must be checked for the specific project.

How SLA helps connect the work

  1. Map the applicable work

    Coordinate with the design and code-compliance team to identify Cx provisions, required design reviews, acceptance tests, forms and responsible providers. Do not treat every project as having the same requirements.

  2. Plan readiness and verification

    Connect the applicable requirements to design records, the Cx plan, system prerequisites and documented functional performance. Schedule specialist acceptance testing with appropriately qualified providers where required.

  3. Close the documentation gaps

    Track required reports, systems information, training records and outstanding findings. Make the document owner and submission route clear before the permit or handoff milestone.

What your project receives

  • An agreed responsibility and documentation matrix for the Cx scope.
  • Readiness, verification and issue records linked to applicable project criteria.
  • An organized Cx closeout package coordinated with separate acceptance-testing records.

Bring to the first conversation

  • Project location, permit timing and applicable code edition
  • Building use, size and new-construction or alteration scope
  • Code-compliance documents, specifications and assigned testing providers

Cx coordination does not automatically qualify a provider to perform every regulated acceptance test. The project must confirm required credentials and responsibilities. The enforcement agency retains its approval authority.

Official references, if you want to go deeperCEC: 2025 Energy Code and compliance resources ↗CEC: published 2025 Energy Code (PDF) ↗
03Adopted codes & jurisdiction requirementsEstablish the governing requirements before defining the tests.

What it means

The model code named in a specification is only part of the picture. State and local adoption, amendments, the permit basis and the project’s systems determine the requirements to review. Examples can include an adopted IECC or ASHRAE 90.1 compliance path, as applicable.

When it matters

Use this review when planning a new facility, renovation or system replacement, particularly when the team works across several jurisdictions. An approach accepted on a previous project may not establish what this project needs.

How SLA helps connect the work

  1. Confirm the basis

    Ask the responsible design and code-compliance team to establish the adopted editions, local amendments, project classification and authority having jurisdiction (AHJ). Document unresolved interpretations for that team to resolve.

  2. Translate requirements into a plan

    Identify the Cx activities, systems, prerequisites and evidence within SLA’s assignment. Distinguish functional verification from contractor QC, startup, TAB, special inspections and other specialist tests.

  3. Track the required record

    Assign each report or certificate to its responsible party. Connect open findings, retests and missing records to the next approval or turnover milestone.

What your project receives

  • A project-specific Cx requirements and responsibility register.
  • Test criteria linked to the approved design and applicable scope.
  • A status record separating completed evidence from open issues or missing submissions.

Bring to the first conversation

  • Site address and permitting jurisdiction
  • Code summary, permit documents and current specifications
  • Inspection/testing assignments and upcoming approval milestones

SLA helps coordinate the Cx work and evidence within its agreed scope. Code interpretation, design compliance and permit approval remain with the responsible design professionals and authorities. A Cx report does not replace those decisions.

Official references, if you want to go deeperU.S. DOE: state energy-code resources ↗
04ASHRAE Cx process referencesGive requirements, responsibilities and verification a shared structure.

What it means

ASHRAE Guideline 0 describes Cx for new buildings and new systems, beginning with the Owner’s Project Requirements. Guideline 0.2 addresses existing buildings, systems and assemblies using the owner’s Current Facility Requirements. Standards 202 and 230 establish Cx process requirements for new and existing work, respectively. Guideline 0.3P is the proposed ongoing Cx guideline and remains in development. Confirm the applicable publications, editions and project requirements.

When it matters

Use a defined process when the team needs a common basis for planning, reviewing, verifying and documenting performance. A standard can be required by an adopted provision or contract; a guideline may also be selected as the project’s agreed approach.

How SLA helps connect the work

  1. Start with the operating need

    For new work, review the OPR and the design team’s BOD. For existing facilities, establish current facility requirements and the records available to support the investigation.

  2. Make the process executable

    Set the Cx scope, roles, review stages, readiness conditions and verification criteria. Connect each planned activity to a requirement and an identified responsible party.

  3. Follow findings through

    Record observations, coordinate correction and retest, and distinguish demonstrated performance from work still awaiting evidence. Carry the agreed information into operator handoff and follow-up.

What your project receives

  • A Cx plan with scope, responsibilities, milestones and document expectations.
  • Review and test records tied to the agreed criteria.
  • An issues record and closeout information that the receiving team can use.

Bring to the first conversation

  • Referenced standards, guidelines and editions
  • OPR/BOD or current facility requirements
  • Contract scope, project schedule and responsibility assignments

A draft or proposed guideline is not a published requirement. Referencing ASHRAE does not mean ASHRAE endorses SLA or certifies the project. Technical acceptance criteria remain specific to the applicable design, requirements and scope.

Official references, if you want to go deeperASHRAE: published Cx references ↗
05GSA & owner-specific criteriaCarry the owner’s operating expectations into the delivered facility.

What it means

Owners can require more than the adopted code or a certification program. GSA publishes federal facility criteria and Cx guidance; universities, healthcare organizations and other owners may define their own standards for systems, documentation, integration and operating handoff.

When it matters

Use this approach when the project must connect to an established owner environment or meet contract-specific criteria. Confirm the documents and revisions incorporated into the project, including applicable GSA criteria where relevant. Do not assume that one owner’s requirements apply to another.

How SLA helps connect the work

  1. Read the owner’s requirements together

    Review the contract criteria, OPR, technical standards and receiving team’s needs. Identify conflicts, missing scope and questions requiring the owner’s direction.

  2. Connect the delivery teams

    Assign interfaces between Cx, design, construction, controls, MSI and operations. Where included, translate Division 25, naming, point data, metering and platform expectations into coordinated responsibilities.

  3. Prepare for use after handoff

    Organize accepted records, open items, systems information and training evidence. Agree who owns follow-up and how outstanding restrictions reach the operating team.

What your project receives

  • An owner-requirements matrix linked to responsibilities and verification evidence.
  • Coordinated interface, documentation and handoff expectations.
  • A closeout record showing demonstrated work, open actions and assigned owners.

Bring to the first conversation

  • Owner standards and contract requirements with revisions
  • OPR, platform/data conventions and systems-manual expectations
  • Facilities contacts, turnover requirements and training needs

Owner criteria and acceptance authority are project-specific. Total building Cx still requires explicit system boundaries and qualified specialists for their assigned work. SLA’s services and deliverables are established in the agreed engagement.

Official references, if you want to go deeperGSA: core building standards and reference documents ↗
06Semiconductor utilities, process interfaces & acceptanceFollow each utility from the facility to the tool, with clear criteria and responsibility at the connection.

What it means

A semiconductor tool depends on the facility services and support equipment around it. The interface record needs to connect the supplier’s utility requirements with the installed facility and the owner’s acceptance criteria. SEMI F122 provides guidance for facilities data packages, including utility connections and interconnections between equipment.

When it matters

Use this guide for a new fab area, tool installation, utility expansion or package-equipment change. Confirm which facility systems, tool interfaces and specialist reviews are included. Facility Cx and process or product qualification are distinct assignments.

Make the connection understandable

The project interface register can address the following, where relevant to the approved scope. The design, supplier and owner establish the actual values and limits.

  • Utility and point of connection: Identify the tool, supporting equipment, service, connection location and the document defining the boundary.
  • Required condition and evidence: Record the applicable pressure, flow, temperature, quality or other criterion, its source and the specialist evidence needed to assess it.
  • Controls and responsibility: Clarify the package/facility signals, permissives, alarms, review assignments and authority for acceptance.

How SLA helps connect the work

  1. Align the documents

    Compare the supplier’s facilities data package with approved drawings, utility schedules and owner requirements. Record mismatches for the responsible design and supplier teams to resolve.

  2. Define readiness at the boundary

    Identify the required installation, quality, specialist testing and documentation prerequisites. Assign who provides each record and who reviews it before the next milestone.

  3. Close the interface record

    Connect authorized verification results, exceptions and approved changes to the correct tool and utility. Keep facility acceptance separate from tool performance and process qualification.

What your project receives

  • A utility and package-interface register with document references.
  • A readiness and evidence matrix with named responsible parties.
  • A record of accepted interface evidence, restrictions and remaining actions.

Bring to the first conversation

  • Tool and support-equipment lists, supplier data packages and utility requirements
  • Approved drawings, connection schedules and owner acceptance criteria
  • Applicable SEMI document editions, specialist assignments and turnover boundaries

SEMI publications are industry standards and guidelines, not blanket regulations for every fab. Confirm the selected documents, editions and their project adoption. Cx coordination does not replace the owner’s process qualification, supplier obligations or qualified safety and specialist evaluations.

Official references, if you want to go deeperSEMI F122: published facilities data-package scope ↗

Clear responsibilities matter. Cx coordinates with contractor quality control, manufacturer startup and the design team. The owner retains acceptance authority; electrical switching and specialist testing remain with qualified, authorized parties.

LET’S TALK ABOUT YOUR FACILITY

Bring us the project.
Or the problem.

A new building, an operating concern or a system that needs to be understood. Tell us what you are trying to accomplish and where the team needs support.

Talk with SLA

SEE WHAT SLA CAN DO.

Enlarged technical illustration

Illustrative only. No live system connection.